Our services i.e. Electrical HV / LV installationis being executed by our highly qualified, efficient, and experienced engineers who are specialized in their respective field. AS Consultant Company provides these services for residential, commercial, hotels, hospitals, malls, offices & fit-out stores, projects & maintenance the entire latest tools and innovative technologies with the industrial / Indian and international norms and standards, We offer these services to the clients at highly affordable prices.

415V Low Voltage Switchgear
Package Substations
11KV Primary and Secondary Switchgear
Oil and Cast Resin Transformers
11KV/0.450KV, 33KV/22KV Distribution switchgear
Busbar Trunking
Commissioning:
After installation of the panels the following commissioning tests can be performed:

Complete functional check of internal panel wiring.
5kV / 2.5 KV, / 1 KV Insulation Resistance test on the panel busbar system
High Voltage AC pressure test on the busbar system of the panels (breakers and disconnectors open).
High Voltage AC pressure test on the busbar system of the panels (breakers and disconnectors closed).
Determination of the current transformers Magnetisation Curves.
Primary Injection of the current transformers (up to 600A).
Primary Injection of the voltage transformers.
Secondary Injection of the protection relays.
No Load & Full Load testing & Commissioning of transformer